How long a garage or extension re-roof takes
A porch or bay-window rubber roof normally completes in half to 1 day, a single garage takes 1 to 2 days, and a full stripped warm-roof rear kitchen extension runs 2 to 3 days in dry weather.
Realistic on-site days for stripping, re-decking, warm-roof insulation and waterproofing, plus how Irish rain affects scheduling.
Free, no obligation. One local roofer prices it, not five.
- half to 1 dayporch or bay-window fit
- 1 to 2 days15–18 m² single garage
- 2 to 3 dayswarm-roof kitchen extension
- Dry deckessential for glue & liquid cure

Typical day-by-day schedule on domestic jobs
Flat roofing moves fast once materials and skip bags are staged on site. Most delays come from waiting for a clean dry weather window rather than slow fitting time.
Porch or bay roof (3–8 m²)
- Day 1 work
- Strip felt, swap soft timber, bond rubber, fix trims & lead flashing
- Day 2 / Day 3 work
- Usually finished Day 1
- Weather sensitivity
- Needs 4 to 6 dry hours
Single garage (15–18 m²)
- Day 1 work
- Strip old felt into skip, replace rotted OSB3 & fix firring strips
- Day 2 / Day 3 work
- Glue single rubber sheet, kerb trims, drip plates & wall flashing
- Weather sensitivity
- Dry deck required on Day 2
Kitchen extension warm roof (25–35 m²)
- Day 1 work
- Strip felt, inspect joists, fit new OSB3 & seal vapour barrier watertight
- Day 2 / Day 3 work
- Lay PIR insulation, bond rubber, dress skylights, trims & lead chase
- Weather sensitivity
- Sealed watertight each evening
Liquid rubber overlay (15–30 m²)
- Day 1 work
- Power-wash moss, repair blisters, prime dry surface & base coat with fleece
- Day 2 / Day 3 work
- Roll final elastomeric topcoat once base coat cures
- Weather sensitivity
- Dry forecast between coats
Price my rubber roof
Four taps show our Irish price guide before we ask for a phone number. One local roofer rings you, not five.
A garage rubber roof, 12 to 20 m², replacing old felt: €2,200 to €3,900, supplied and fitted.
How this roof guide is worked out
The range reflects typical Irish supply-and-fit rubber roofing rates (13.5% residential VAT) for that structure, footprint and existing surface. Bare timber figures cover rubber membrane or liquid coating, adhesives, perimeter drip trims and labour on a sound OSB3 or plywood deck. Choosing old leaking felt adds an allowance for stripping, disposal and localised deck prep. Full rotten board replacement (€30 to €60/m²), Part L warm-roof PIR insulation (€40 to €80/m²) and upper-floor scaffolding are confirmed after a local roofer inspects the roof.
How roofers keep your house dry during unpredictable weather
Homeowners naturally worry about stripping an extension roof over a fitted kitchen in Ireland. Good flat roofers never strip more area than they can deck and seal with a self-adhesive vapour control layer before evening. That vapour barrier acts as an immediate temporary waterproof roof overnight, letting insulation and rubber membrane proceed cleanly the next dry morning.
- Ask for a dry-window start rather than a rigid rainy date. Pressuring a roofer to glue rubber onto wet timber causes adhesion failure later.
- Clear cars from the drive on strip-out morning. Keeping van and skip access straight beside the garage shaves hours off carrying old bitumen and OSB3 sheets.
- Confirm scaffolding lead time for dormers. Tower setup usually goes up the afternoon before roofing starts and clears the day after sign-off.
Questions homeowners ask
How soon after booking can an Irish flat roofer start?
Outside major winter storm surges, most local flat roofers schedule single garages and extensions within 1 to 3 weeks, slotting work into the next dry forecast spell.
Can rubber roofing be fitted in cold winter temperatures?
Cold dry days above 5°C are fine for solvent contact adhesives and moisture-cured polyurethane liquid systems. Water-based deck adhesives slow down sharply below 5°C, so winter jobs often switch to all-weather contact adhesive or cold-cure liquid systems.
Do I need to be home while the flat roof is replaced?
Only at the start for side-gate access and outdoor power if needed, and at completion to inspect neat trims, clear gutters and review your written warranty.
How long after fitting a liquid rubber roof is it rainproof?
Modern moisture-cured polyurethane coatings typically become shower-resistant within 1 to 2 hours of rolling, though full cure for foot traffic takes a full day.
All rubber roofing pages and guides
Domestic flat roofs
Homeowner guides

Book your dry-weather slot with one local roofer
Check your m² estimate first, then arrange a quick ladder check and start window with a single flat roofer in your county.